Ameren Illinois introduced Aug. 5 that the Illinois Commerce Fee granted a certificates of public comfort and necessity for its Central Illinois Grid Transformation Program. The approval clears the way in which for building later this 12 months on 380 miles of 345-kilovolt transmission strains, three new substations and upgrades to 5 present substations throughout 13 counties as a part of a $1.6-billion improve.
The venture stems from the Midcontinent Impartial System Operator (MISO) 2024 Lengthy-Vary Transmission Plan Tranche, which recognized important bottlenecks within the Midwest grid.
The brand new strains can be co-located alongside present Ameren corridors throughout 13 central Illinois counties—from the Mississippi River at Quincy via the Peoria metro space to Tazewell County.
Eight substations—three new services at Camp Level, Kenney and Piper Metropolis and 5 rebuilt or expanded stations in Brown County, Pontiac, Gibson Metropolis, Iroquois County and Peoria—can be tied into the community, with upgraded communications and supervisory management and knowledge acquisition programs to watch and management gear remotely.
“At a time when the Midwest faces a persistent scarcity of the electrical energy wanted to satisfy rising demand, this important venture will present vitality entry and certainty for companies and residential progress,” mentioned Shawn Schukar, chairman and president of Ameren Transmission Co. of Illinois, in an organization launch.
Ameren filed its joint petition in January 2024 (ICC Docket 24-0088), submitting detailed routing maps, a preliminary cost-benefit evaluation and wetland evaluation summaries. Fee workers issued 25 knowledge requests, probing right-of-way acquisition plans, load-flow modeling, environmental mitigations and coordination with third-party infrastructure homeowners.
Map courtesy of Ameren Illinois
Public hearings in Springfield in Might 2024 drew testimony from private-landowner teams and particular person witnesses who steered alignment tweaks. Nevertheless, fee workers, together with Ameren engineers, mentioned such deviations would increase prices by 2%–4% or require new substation work, and accepted the unique alignment as “crucial to take care of reliability and assist future load progress.”
A number of commenters raised land‐use and well being issues: James Williams, whose Iroquois County farm borders a 138-kV line, urged the fee to “use present rights-of-way” quite than take new farmland. Matthew Hadsall of Peoria County warned, “My best concern as a father of seven youngsters is their well being dwelling near high-voltage energy strains,” and requested for a quarter-mile residential setback.
Ameren responded that “present environmental controls and species-protection measures meet all state and federal necessities” and that bundle deviations may improve prices or complicate substation design.
Pooled analyses have discovered that youngsters in houses with common extraordinarily low-frequency magnetic fields above 0.3–0.4 µT—ranges widespread inside about 100 m of main transmission strains—face roughly twice the chance of childhood leukemia, and the Worldwide Company for Analysis on Most cancers classifies these fields as probably carcinogenic to people (Group 2B).
Nonetheless, main well being companies preserve that routine residential exposures pose little substantiated threat: the World Well being Group experiences “no substantive well being points” at environmental discipline ranges, and the U.S. Environmental Safety Company notes that research haven’t persistently demonstrated adversarial results at typical publicity ranges.
Detailed plans accompanying the petition that ENR reviewed present that new and upgraded circuits will cross or parallel 42 railroad segments, 16 main pipeline corridors and 78 present high-voltage circuits inside half-mile buffers, requiring coordination with greater than 100 infrastructure homeowners. Discover was despatched beneath ICC Rule 305.60 to all affected railroads and utilities.
In its July 2 closing order, the fee imposed two circumstances: Ameren should file quarterly updates on right-of-way negotiations, and submit a closing wetland-mitigation plan not less than 90 days earlier than starting work in any county.
The utility additionally should safe native zoning and constructing permits, full endangered species and cultural-resource critiques, and finalize MISO interconnection research earlier than mobilizing in mid-2026.
Challenge administration can be dealt with by an inner Ameren companies group, using union contractors and native subcontractors for line work, substation meeting, surveying and street monitoring. Easement negotiations are led by Emerald Power & Exploration, Volkert and Contract Land Providers.
Price allocation splits roughly $1.29 billion in transmission-plant prices into $1.225 billion borne by Ameren Transmission Co. and $66 million by Ameren Illinois, with 91% charged to the broader MISO Midwest sub-region and eight.87% to downstate prospects.
“Once we improve system capability, everybody wins,” Thomas Pauk, venture supervisor for this system, stated in the release. “Opening new vitality pathways promotes decrease prices sooner or later and helps maintain buyer charges reasonably priced.”
Key milestones embody the primary right-of-way standing report due Oct. 1; preliminary mobilization in November; Adams County wetland-mitigation plan due Dec. 3; main-line stringing and tower erection mid-2026; and phased energization via late 2029.
ENR contacted Ameren for added particulars on awarded contractors, substation technical specs, efficiency targets and workforce projections. Brad Brown, a spokesman for Ameren, mentioned the corporate couldn’t present these particulars earlier than press time however added, “I’ll make clear the $1.6 billion price estimation is inclusive of a phase that goes into Missouri; the Illinois Commere Fee price estimate is for just below $1.3 billion.”
Trending Merchandise
CRAFTSMAN Pliers, 8 & 10″, 2Piece Groove Joint Set (CMHT82547)
TT TRSMIMA Safety Harness Fall Protection Upgrade 4 Quick Buckles Construction Full Body Harness 6 Adjustment D-ring
BIC Wite-Out Brand EZ Correct Correction Tape, 19.8 Feet, 4-Count Pack of White Correction Tape, Fast, Clean and Easy to Use Tear-Resistant Tape Office or School Supplies